The Royal (Dick) School of Veterinary Studies

Campus Developments

As the Campus goes through its next phase of Development from 2015 to 2017 there may be times when there is disruption to the campus, or information which we need to share with staff. This page will be updated on a regular basis to share this information.

Week commencing 21st August 2017

Live Projects:

  1. Roslin Innovation Centre and Campus Hub (Centre Building)
  2. Easter Bush Energy Centre   
  3. EDSCCU Project (Equine Diagnostic, Surgical and Critical Care Unit)
  4. Large Animal Research and Imaging Facility (LARIF)

 

1. Roslin Innovation Centre and Campus Hub (Centre Building)

Contractors Onsite:            

McLaughlin & Harvey Construction Ltd

Working Hours:                   

07:00 – 19:00 Monday – Thursday,

7:00 – 19:00 Friday

08:00 – 16:30 Saturday & Sunday

Operatives (approx.):           20+

Activities taking place:       

Testing and commissioning of services.

Decorative finishes and cleaning throughout over the weekend (19th / 20th).

Continuation of landscaping works, including the pouring of concrete bases and the installation of aluminium edgings.

Continuation of retaining wall and footpaths to the south of the building.

There will be various pieces of equipment delivered throughout next week. The majority of these will be delivered into the site via the ramped entrance adjacent to the old stable block (at the FAP / Equine Hospital car park) and will be early in the morning. There will be gym equipment delivered on Tuesday (22nd) to the building via the courtyard area adjacent to the Roslin Building.

Location of works:               

Compound by Greenwood Building

Centre Building Site                       

Spare plot adjacent to the Bumstead Building (occasional forklift and pick-up truck operating between this area and main site).

********************************************************

2. Easter Bush Energy Centre

Contractors Onsite:  Vital Energi

Working Hours: 

Monday – Thursday, 07:30-17:30.

Friday, 07:30-15:30.  

08:00 – 16:30 Saturday and Sunday 

Operatives (approx):  13 operatives, 3 management staff

Activities taking place:       

Commissioning and testing.

 Flushing of heating and cooling pipework.

  Ongoing reinstatement works.

Scottish Power meter installation.

Ongoing works to install the risers at the Roslin Building. Please note that works described previously, which effected fire egress within the Roslin Building, have been delayed by 1 week. The following info details the revised programme.

Works will continue in the excavated area to the rear of the Roslin Building next week. This may, on occasions, generate some noise and vibration. The following week, commencing on the Saturday 26th, the works will progress onto the installation of the pipework running vertically up the building. Unfortunately, with this phase of work, a degree noise disturbance is unavoidable. This has been coordinated with the BRF and works will be planned to avoid disturbance during the most sensitive periods. If you have any questions on this or if this is a cause for concern then please get in touch with me.

On the weekend of the 26th and 27th August, Vital will need to remove the temporary bridge at the fire escape to the rear (South East) of the Roslin Building. Consequently, as happened previously, the escape will be blocked off and alternative means of escape should be used in the event of an emergency. The plans attached detail the changes in egress routes. Fire egress will return to normal as of Monday (28th).   

 

Location of works:               

Scottish Enterprise’s land to south eastern corner of the University’s Campus 

Energy Centre Site

Central line through campus.

 

********************************************************

3. EDSCCU Project (Equine Diagnostic, Surgical and Critical Care Unit)

Contractors Onsite:             

McLaughlin & Harvey Construction Ltd

Working Hours:                   

Monday – Friday, 07:00-18:30.

Operatives (approx):           

15 and 1 Site Manager

Activities taking place:       

Internal decoration.

Commissioning and snagging.

Soft and hard landscaping around building.

Dismantling of hoarding around site compound.

Location of works:               

EDSCCU Site.

********************************************************

4. Large Animal Research and Imaging Facility (LARIF)

Contractors Onsite:             

Robertson Construction

Working Hours:                   

Monday – Friday, 07:00-18:00.

Operatives (approx): 17

Activities taking place:       

Continuing drainage works.

Continuing with steel erection including the grouting of columns.

There will be large steel deliveries on the mornings of Monday and Thursday.

Access road verge maintenance.  

********************************************************

5. Cottage Demolition (Nursery site)

Contractors Onsite:             

G&J Ltd Demolition Working Hours:                   

Monday – Friday, 07:00-17:00.

Operatives (approx): 4

Activities taking place:       

Site set up

Site clearance.

Please note that the pavement in front of the cottages has been closed, to allow work to commence. 

********************************************************

 

General issues:  

Works vehicles to use Campus’ south entrance/exit only.

Designated contractor parking located within the top end of the “Red” car park.

I have included a map showing the available pedestrian access routes throughout the campus. I will update this as access changes.

As you can see above the Cottage Demolition project will commence on Monday. Access to the site will be on the Roslin Car Park access road, opposite the cottages. The access will be close to the roundabout and vehicles will need to reverse into site. Banksmen will assist with this manoeuvre. With this in mind please approach this area with caution. Most deliveries will be early in the morning.  

 

Thank you in advance for your cooperation, if you have any concerns with any of the above then please do not hesitate to contact me. Rob Lee, Easter Bush Site Coordinator (Estates Team), Mobile: 07825 120782, Email:Rob.Lee@ed.ac.uk

 

Works stated in this update are weather dependent and therefore are liable to change.

Thank you in advance for your cooperation, if you have any concerns with any of the above then please do not hesitate to contact me. 

Rob Lee

Easter Bush Site Coordinator (Estates Team)

Mobile: 07825 120782

Email:Rob.Lee@ed.ac.uk