FW1 latest update: 24 June 2011

An end is nearing for Free Weights 1 completion with an expected handover date of Wednesday 29 June 2011.

Some finishing works will then conclude with an expect re-opening on Monday 11 July. Details as follows:

  • Friday 24 June: painting commences
  • Wednesday 29 June: handover
  • Thursday 30 June: deep clean of room
  • Monday 3 July: equipment returned to room
  • Wednesday 6 July: GL Floors to sand and seal platforms
  • Friday 8 July: positioning and final clean
  • Monday 11 July: expected re-open

We would like to thank all Free Weights users once again for their patience during this process.